Page 1 of 1
Columbia University – Havemeyer 600 Commissioning
Project:
CU – Havemeyer 600
Document Reviewed:
BMS Submittals
Project No.:
CUH-CX-000
Document Issued Date:
October 22nd, 2014
Parties Involved:
SHG, CU, Hellman, Subcontractors
Revision & Date:
th
Set #2 – November 4 , 2014
Syska expressly disclaims any and all responsibility, liability and /or exposure with regard to the design and construction of this project and the client understands and acknowledges that the corrections or comments made on the submittals during this review only address aspects in connection with the commissioning scope and do not relieve contractors and/or the designer from compliance with the requirements of the drawings and specifications.
Item
No.
1.
2.
Submittal Description
Description: BMS Submittal (Drawings)
Filename: Combined ATC Drawings Submittal #2 - 10-22-14
Issuing Party: Hellman Construction Co., Inc.
Issuing Vendor: Energy Management Control Corp.
Submittal Date: 10/22/14
Description: BMS Submittal (Sequence of Ops & Data Sheets)
Filename: Part 1 ATC SOP Submittal #2 - 10-22-14
Issuing Party: Hellman Construction Co., Inc.
Issuing Vendor: Energy Management Control Corp.
Submittal Date: 10/22/14
Comments
1)
AHU Flow diagram and wiring diagram (Pages 4 & 5) show that the BMS has a digital output to start/stop EF-603. SOO section B.1 states that fume hood exhaust fan shall be manually started and stopped via local starters.
2)
AHU Flow diagram and wiring diagram (Pages 4 & 5) should have air flow monitoring
stations