№ | DESCRIPTION | Action | Date | 1 | Meeting held between Pall and Crescent Petroleum to identify critical points, potential hold ups, clarify any open commercial and technical points, and introduce team members | Info | | 2 | Pall Stated that engineering clarification was on going to have a clear start once P.O is received. | Info | | 3 | Pall will submit preliminary P&ID identifying scope of supply, preliminary skid 3D model and GA showing dimensions, Supplier Document register ( SDR) within three business days | Pall | 10-Jan-2013 | 4 | Project fabrication schedule will be submitted two weeks from formal P.O from Crescent to Pall | Pall | TBA | 5 | Pall proposed conducting a design review meeting once P&ID’s have been submitted in order to close any open points or areas of discussion timely. | Info | | 6 | Pall requested clarification on the type of control valves supplied for the project. Both Pall and Crescent confirmed that the liquid phase drain valves supplied will be on/off type valves | Info | | 7 | Pall and Crescent agreed that P&ID’s by Pall will reflect the valves BOQ stipulated on the technical proposal. | Info | | 8 | Pall requested Crescent team to provide area of clarifications drawings. | Crescent | | 9 | Crescent clarified the requirement in