The learning objectives that were advanced this following week were safety, project planning, project administration, and craft training.
Learning objectives are assigned to me when the matter arises.
There have been large quantities of rain deposits on the site due to the rain this past week. A concrete pour was scheduled for this week, but had to be postponed because the carton forms would have been ruined by the ground moisture. A solution to this was to wrap the carton forms with plastic wrap so moisture would not compromise the rigidity